# CE Practice Exam #1 - Case Study 2 Question 6

**URL:** <https://community.blackspectacles.com/t/ce-practice-exam-1-case-study-2-question-6/6607>\
**Category:** Construction & Evaluation\
**Created:** [March 1, 2025, 5:46pm UTC](https://community.blackspectacles.com/t/ce-practice-exam-1-case-study-2-question-6/6607 "2025-03-01T17:46:47Z")\
**Posts on this page:** 4\
**Page:** 1

<div class="post-metadata">

**Author:** ![spinski](https://blackspectacles.com/uploads/images/26.png) [@spinski](https://community.blackspectacles.com/u/spinski)\
**Post date:** [March 1, 2025, 5:46pm UTC](https://community.blackspectacles.com/t/ce-practice-exam-1-case-study-2-question-6/6607/1 "2025-03-01T17:46:47Z")

</div>

A practice question asks to determine the new date of installation for bike racks if the racks now have a 2-week (calendar day) delay. The original install timeline was April 25 - April 30 (5 days).

I thought the two weeks would be _added_ onto this schedule, making the installation complete on May 14 (5 days + 14 days). Instead, the correct answer was May 9th (14 days total). Why are those 5 days of construction from 4/25-4/30 no longer included in the timeline?

---

<div class="post-metadata">

**Author:** ![kiaragalicinao](https://yyz1.discourse-cdn.com/flex029/user_avatar/community.blackspectacles.com/kiaragalicinao/32/1607_2.png) [@kiaragalicinao](https://community.blackspectacles.com/u/kiaragalicinao)\
**Post date:** [March 3, 2025, 10:58pm UTC](https://community.blackspectacles.com/t/ce-practice-exam-1-case-study-2-question-6/6607/2 "2025-03-03T22:58:02Z")

</div>

Welcome to the ARE Community, @spinski! Thank you for reaching out with your question.

We actually have an existing thread related to this specific question:

> [@Schedule, Lead time + contigency. A twisted sum](https://community.blackspectacles.com/t/schedule-lead-time-contigency-a-twisted-sum/6192):
>
> I’m really stuck in the Case Study#2 Question #6 of the randomized exam (Transportation Hub in a Small Rural Town) Question ask for the earliest date for install Bike Racks. I’m unable to follow the math of the response: If Lead Time, as per RFI is 6 weeks, the activity, per schedule is 6 calendar days, why they are displacing the commencement date only 2 weeks? Besides, question #3 in same Case Study displace another activity one week based on the contigency stated in same Schedule (same res…

For reference, you can use the search bar on the ARE Community home page to search for key terms. If you are struggling with a topic, there is a good chance someone else is too 🙂

Hope this helps! Let me know if you need further clarification.

Kiara Galicinao, AIA, NCARB  
**Black Spectacles**

---

<div class="post-metadata">

**Author:** ![spinski](https://blackspectacles.com/uploads/images/26.png) [@spinski](https://community.blackspectacles.com/u/spinski)\
**Post date:** [March 16, 2025, 5:59pm UTC](https://community.blackspectacles.com/t/ce-practice-exam-1-case-study-2-question-6/6607/3 "2025-03-16T17:59:45Z")

</div>

Thanks, I reviewed the existing thread, but the answer doesn’t address why the additional 2 weeks wasn’t added onto the original 5 days held for installation.

---

<div class="post-metadata">

**Author:** ![kiaragalicinao](https://yyz1.discourse-cdn.com/flex029/user_avatar/community.blackspectacles.com/kiaragalicinao/32/1607_2.png) [@kiaragalicinao](https://community.blackspectacles.com/u/kiaragalicinao)\
**Post date:** [March 21, 2025, 7:23pm UTC](https://community.blackspectacles.com/t/ce-practice-exam-1-case-study-2-question-6/6607/4 "2025-03-21T19:23:48Z")

</div>

Hi @spinski,

To reiterate what was mentioned in the previous post, the project schedule reflects bike rack installation only - it does not specify which type of bike rack is being proposed here or what the lead time is. Therefore, we need to determine what effect(s) in-ground bike racks would have on the schedule, if any. Does it align with the proposed installation date or does it push the schedule back?

The RFI indicates that in-ground bike racks have a 6-week lead time (resulting in a schedule change) and surface-mount bike racks have a 4-week lead time (resulting in no schedule change). Therefore, we can assume that the project schedule aligns with using surface-mount. If we use in-mount, the lead time increased by 2 weeks and in turn, pushes the installation back by 2 weeks.

The reason why we do not need to add this original 5 day of installation time to the delay is because it was already factored into the schedule. If we were to use surface-mount bike racks, there would be no schedule change (4 week lead time + 5 days total of installation). If we proceed with the in-ground bike racks, we would be delayed (6 week lead time + 5 days total installation). To consider what the overall effect on the schedule is, we take the difference between these two, which is a total of 2 weeks.

I know it’s super confusing and while simple math is involved, it really is a puzzle. For these types of questions, I recommend drawing a diagram or chart to help you visualize the schedule adjustments and effects.

Let me know if you have any further questions!

Kiara