# Incorrect wording

**URL:** <https://community.blackspectacles.com/t/incorrect-wording/4289>\
**Category:** Practice Management\
**Created:** [May 15, 2022, 10:12pm UTC](https://community.blackspectacles.com/t/incorrect-wording/4289 "2022-05-15T22:12:08Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![Gfeldman](https://blackspectacles.com/uploads/images/5.png) [@Gfeldman](https://community.blackspectacles.com/u/Gfeldman)\
**Post date:** [May 15, 2022, 10:12pm UTC](https://community.blackspectacles.com/t/incorrect-wording/4289/1 "2022-05-15T22:12:08Z")

</div>

A question from the ARE 5.0 Practice Management Practice Exam is below. I think we want Work?

An architect is preparing an agreement with a new client for a proposed healthcare facility. According to AIA Owner-Architect agreements, which of the following are owner’s responsibilities? \*\*Check the four that apply.

1. Furnishing civil surveys

Correct. The owner is responsible for furnishing surveys to describe legal and physical characteristics of the project site.

1. Providing and updating the project budget

Correct. The owner is responsible for establishing and updating the budget for the project throughout its duration until final completion. This includes: cost of qork, owner’s other costs, and reasonable contingencies related to cost.

---

<div class="post-metadata">

**Author:** ![coachrebeccasmith](https://yyz1.discourse-cdn.com/flex029/user_avatar/community.blackspectacles.com/coachrebeccasmith/32/1338_2.png) [@coachrebeccasmith](https://community.blackspectacles.com/u/coachrebeccasmith)\
**Post date:** [May 16, 2022, 3:16pm UTC](https://community.blackspectacles.com/t/incorrect-wording/4289/2 "2022-05-16T15:16:05Z")

</div>

Hi @Gfeldman !

Thanks so much for pointing that out to us, I will inform the team and we will fix that typo!

-Rebecca
