# Negotiating supplemental services per B101

**URL:** <https://community.blackspectacles.com/t/negotiating-supplemental-services-per-b101/7397>\
**Category:** Practice Management\
**Tags:** practice-quiz\
**Created:** [August 1, 2025, 2:01pm UTC](https://community.blackspectacles.com/t/negotiating-supplemental-services-per-b101/7397 "2025-08-01T14:01:38Z")\
**Posts on this page:** 4\
**Page:** 1

<div class="post-metadata">

**Author:** ![christopherbwatkins92](https://yyz1.discourse-cdn.com/flex029/user_avatar/community.blackspectacles.com/christopherbwatkins92/32/1796_2.png) [@christopherbwatkins92](https://community.blackspectacles.com/u/christopherbwatkins92)\
**Post date:** [August 1, 2025, 2:01pm UTC](https://community.blackspectacles.com/t/negotiating-supplemental-services-per-b101/7397/1 "2025-08-01T14:01:39Z")

</div>

When determining supplemental services for the B101 contract, and there is a question that asks “which services would the architect suggest”? how do we determine which answers are correct?

I understand that an architect has responsibilities for certain services, such as programming, their consultants, etc. and the owner has their responsibilities, such as land acquisition, civil engineers, and hazardous material items. However, when a question like this is asked, how do we select the correct answers based on whether its the architect’s responsibilities to perform the work, or if it’s the owner’s responsibilities?

Reference:

Objective 2.3: Select and Apply Practice Strategies for a Given Business Situation and Policy

---

<div class="post-metadata">

**Author:** ![kiaragalicinao](https://yyz1.discourse-cdn.com/flex029/user_avatar/community.blackspectacles.com/kiaragalicinao/32/1607_2.png) [@kiaragalicinao](https://community.blackspectacles.com/u/kiaragalicinao)\
**Post date:** [August 12, 2025, 6:46pm UTC](https://community.blackspectacles.com/t/negotiating-supplemental-services-per-b101/7397/2 "2025-08-12T18:46:50Z")

</div>

Hi @christopherbwatkins92, thanks for your question! There isn’t a universal response to this question, as it really depends on the specific scenario presented. You’d want to consider the project type and scope, as well as other factors relevant to the discussion (i.e. services already provided by the owner). The question is less about who (architect or owner) is providing which service, but more about whether the service is relevant to the project or not.

Take a look at the answer explanations for both correct and incorrect answers in PcM Quiz Break 10, as we’ve provided reasonings for why each supplemental service should be suggested (or not) in relation to specific factors in the given scenario.

Hope this helps!

Kiara Galicinao, AIA, NCARB  
Product Coordinator  
**[Black Spectacles](https://www.blackspectacles.com/en-us/)**

---

<div class="post-metadata">

**Author:** ![Citrillion](https://yyz1.discourse-cdn.com/flex029/user_avatar/community.blackspectacles.com/citrillion/32/1579_2.png) [@Citrillion](https://community.blackspectacles.com/u/Citrillion)\
**Post date:** [August 16, 2025, 7:28pm UTC](https://community.blackspectacles.com/t/negotiating-supplemental-services-per-b101/7397/3 "2025-08-16T19:28:24Z")

</div>

@kiaragalicinao Would this be considered an A/E (Analyze & Evaluate) type of question?

---

<div class="post-metadata">

**Author:** ![kiaragalicinao](https://yyz1.discourse-cdn.com/flex029/user_avatar/community.blackspectacles.com/kiaragalicinao/32/1607_2.png) [@kiaragalicinao](https://community.blackspectacles.com/u/kiaragalicinao)\
**Post date:** [August 22, 2025, 6:53pm UTC](https://community.blackspectacles.com/t/negotiating-supplemental-services-per-b101/7397/4 "2025-08-22T18:53:10Z")

</div>

@Citrillion yes, this could certainly be considered an A/E type of question, as you’re required to analyze the given information, then evaluate services to determine which are relevant (and prioritize).