CE | Addressing Safety, Progress, and Claim Issues [Exercise A]

@Harshika.Seth wrote in with this question:

It is important to note why the work was uncovered, as the result depends on the specific scenario.

Per A201 §12.1.2, there are two key scenarios:

  • If the contractor covers work without giving required notice or against a request to inspect → the contractor must pay to uncover it, even if the work is correct.

  • If the work was properly exposed for inspection and then later the architect requests it be uncovered again → if the work is found to be in conformance, the owner pays.

In this case, the contractor installed the roofing despite a request to inspect first, so they didn’t follow the required process. That’s why the contractor bears the cost, even though the work was acceptable.

Kiara Galicinao, AIA, NCARB