A101 4.2.1 Alternate vs 4.2.2 Alternate

Here is my understanding - does this seem right?

4.2.1 Alternate:The Owner is 100% committed to having this in the Project. He would have to amend the contract to remove the alternate.

4.2.2 Alternate: The Owner is not certain if he will be able to have it in the Project. He would have to amend the contract to include the alternate.

Timing:

Alternate (or change) decided before bids come back: Addendum

Alternate known after bids come back but before signing: 4.2.1

Alternate known after signing: 4.2.2

You summed it up great, @aidenjh!