A practice question asks to determine the new date of installation for bike racks if the racks now have a 2-week (calendar day) delay. The original install timeline was April 25 - April 30 (5 days).
I thought the two weeks would be added onto this schedule, making the installation complete on May 14 (5 days + 14 days). Instead, the correct answer was May 9th (14 days total). Why are those 5 days of construction from 4/25-4/30 no longer included in the timeline?
Welcome to the ARE Community, @spinski! Thank you for reaching out with your question.
We actually have an existing thread related to this specific question:
For reference, you can use the search bar on the ARE Community home page to search for key terms. If you are struggling with a topic, there is a good chance someone else is too
Hope this helps! Let me know if you need further clarification.
Thanks, I reviewed the existing thread, but the answer doesn’t address why the additional 2 weeks wasn’t added onto the original 5 days held for installation.