Confusing answer

The question clearly notes that all but ONE bid came in over budget. The answers proceed as if all bids were over budget. The selection choices are as follows:

  • I. Authorize the project to be rebid
  • II. Approve an increase in the owner’s budget and accept the lowest bid
  • III. Approve an increase in the owner’s budget and accept another submitted bid
  • IV. Consult with the architect to revise the project scope, quality, or program to reduce cost

AIA B101 Section 6.6 permits the owner to authorize rebidding or work with the architect to revise the project scope, quality, or program when bids exceed the budget. However, the owner may also increase the budget and accept one of the submitted bids.

Item II notes as if there were no bids on budget and feels like it should be wrong. Why would you increase the budget to accept the lowest bid when you can do so without increase?

I read it the same way. If exactly one bid is at or under budget and every other bid is over budget, that one bid must be the lowest bid. So accepting the lowest bid would not require a budget increase; option II adds an unnecessary step and looks internally inconsistent. If the exam treats II as correct, either it assumes “lowest bid” means the lowest over-budget bid, or the option is poorly worded.

@relempago Thanks for your patience, and great catch!

I checked with Marissa Yee, one of our architects, and here’s her take:

I agree with the member that answer II is confusing.

We’re looking into this question (CSE Practice Exam Form 2, ID 7001166) and will make any necessary edits.

And if there’s anything that would help you study and pass, I’m here to help.