Thanks to everyone who attended today’s workshop.
I wanted to follow up on the question about the design fee versus the construction administration fee.
The workplan given only focuses on the design portion of the project. The effort for construction administration in terms of fee and duration is very different from the effort for design. Most of the architect’s fee is dedicated to design.
When calculating the fee for each design phase based on the phase duration, this has to be factored as a percentage of the design phase only.