One question, if architect notice something wired on the site (EX: equipment undersized, wrong beam size…), apart from writing into the field report, should he/she notify the contractor immediately as well?
Thanks!
Hi ARE community,
One question, if architect notice something wired on the site (EX: equipment undersized, wrong beam size…), apart from writing into the field report, should he/she notify the contractor immediately as well?
Thanks!
@coachglennparks do you mind helping @whuang
Hi Whuang,
Simple answer is yes. The architect should notify the General Contractor and Owner following observations where things are not consistent with the contract documents.
-CoachGlenn.