ARE Live: Construction & Evaluation Mock Exam '22

@kaitlin the website below is also pretty handy!

2 Likes

You can read more about the G704 - Certificate of Substantial Completion at the link below:
https://www.aiacontracts.org/contract-documents/155061-certificate-of-substantial-completion

You can also review the preview of this document here: https://help.aiacontracts.org/public/wp-content/uploads/2020/12/AIA-G704-2017-Sample.pdf#_ga=2.149492606.915258824.1645121537-605697607.1645121537

Thank you for clarifying!

1 Like

thank you

1 Like

Do you offer a discount code for BS? Did I miss it? I thought they give it out at the end of the live session.

@piperschad

Hi,
Thank you Black Spectacles team for a great session.

The wording sometimes gets me tripped up as well. For the first question, is a change order the best answer because the contractor is involved?

I chose Construction Change Directive because at the shop drawing phase, we may be pressed for time.

Thanks,
Taylor

1 Like

Expanding on the initial question - does the Substantial Completion Exception typically close out the issue contractually? For some reason it seems like temporary fix to defer resolution. Would this ultimately make it into as-builts/ record drawings?

Hi @tnsmueller ,

Hope you’ve been well!

A construction change directive is used to ensure the work continues when the owner, architect, and contractor cannot agree on either the time or fee associated with a change to contract sum, schedule, or scope.

A change order is the correct answer because hopefully all parties agree on the adjustment. A construction change directive may be needed if the contractor demands a sum the architect/owner think is egregious for the change, but baring additional information stating as much in the scenario, a change order should always be the first step.

It’s likely you won’t see any construction change directives given until the work begins.

You can review more information about change orders and construction change directives in the A201. See snippet of Article 7 “Changes in the Work” below for reference!

https://help.aiacontracts.org/public/wp-content/uploads/2020/05/Preview_A201-2017.pdf#_ga=2.250148686.915258824.1645121537-605697607.1645121537

Hope this helps,
-Darion

Hi Kaitlin! While we currently do not have any sales or discount codes available at this time, we have worked a discount into the pricing of our 6 and 12-month subscriptions.

https://go.blackspectacles.com/pricing/individual

1 Like

Hi @peter.sushch ,

The contractor should note the changes on their construction set. Remember, the architect does not provide as-builts or record drawings as a basic service (check out Article 4 of the B101). If they are requested to be provided by the architect then the architect should update their drawings to reflect the built condition.

Contractually, the owner’s written acceptation of the condition is required - listing the rail on the certificate of substantial completion is one example of how this could be done. In the case of the question, the cost difference between the wood and painted rail likely is low in the grand scheme of construction. If the accepted condition was relatively costly, it’s likely a change order would be produced reducing the contract sum.

Here’s some sections from the A201 related to accepting non-conforming work:


Hope this helps!

1 Like

Huh. Okay that is unfortunate. For someone who needs a discount, buying more isn’t really helpful. Thanks anyway.