NCARB CE Practice exam:
On November 14th, temperatures are expected to drop below freezing at the multifamily condominium project site. Temperatures will return to above freezing by November 16th. Which of the following suggestions should the architect make to the contractor to keep the project on schedule?
-
Check the three that apply.
A. Delay plumbing rough-in
B. Reschedule cabinet installation
C. Delay drywall taping and painting
D. Provide temporary heating to interior spaces
E. Continue with the floor underlayment installation
F. Reschedule concrete sealing for November 16th or 17th
Every single one of these options means I as the Architect am now engaging with the Construction Schedule and in the case of providing the temp heat to help the drywall mud cure - I’m getting into means and methods.
I got this practice exam question right - but the whole time I was thinking ’
“NCARB shouldn’t have even allowed this question to go out in the first place. It’s a total negation of what they’ve been hammering in this whole time - we do not get involved with Construction Scheduling…”
Am I missing something here?