PcM Practice quiz

Yes of course! This has been updated. Thank you

1 Like

in C401 just said that Consultant should be paid promptly after the architect gets paid, it didn’t mention about paid by monthly. In B101, article 11 talks about the compensation method for architect to get fees, but it also doest talk about how architect gets paid specifically. In AHPP, page 971 discuss the ways for architect to charge to their services. So if we just based on the AIA contract, How do we know how architect gets paid ?

1 Like

Thank you!

Hi @ngand8629 ,

Per the B101 there are two standard ways the architect can be compensated: stipulated some or percentage basis. There is also a line for “other”.
image

The owner and architect negotiate the fee and then fill out the compensation in the appropriate line. I would assume the architect is likely being compensated either as a stipulated sum or percentage basis if they are using the B101.

I responded to another question about when the architect is compensated on a percentage basis awhile back if you’re interested in reading more about it: Architectural Fee - #3 by coachdarionziegler

Hope this helps!
-Darion

1 Like

For Quiz Question 14: Is it allowed to calculate utilization rate in Dollars / Dollars? all the material I had seen was pointing to the formula as HRS / HRS (AHPP Page 417) I would have assumed a long form calculation based on the yearly 2080 hrs and go from there? Is it interchangeable?

@coachdarionziegler

1 Like

Hi @miriam.a.cotto ,

Great question!
The utilization rate is typically calculated based on the amount of hours worked per the AHPP. This question is tricky because it is giving you other values that you can use to extrapolate this information.

In Question 14 it is listing the direct labor expenses and the total salary expenses. This ratio is equal to the ratio of the billable hours vs the the total hours of each employee. This is because the direct labor expense (the total amount of the salary that is being paid for billable work in this instance) is directly proportional to the billable hours of an employee. The total salary expense (the total amount the employee is being paid) is directly proportional to the total hours an employee is working (typically 2080 a year).

salary being spent on billable labor/total salary received = billable hours/total hours

Hope this helps!
-Darion

1 Like

Lots of typos here which led to some confusion.

Question 71 is incomplete.
(No numbers were given to calculate)

Question 76 has a math error under the answer explanation
(Baltimore, Maryland: $8,500,000 - $5,300,000 = $5,900,000).

Question 77 has another math error in the explanation
($5,400,000 / $2,600,000 = 0.481)

Hi @Stephen !

Thanks for pointing out those typos to us! I’m tagging @coachchrishopstock so we can get those corrected. Thanks again!

-Rebecca

Thanks @Stephen and @coachrebeccasmith for bringing these to my attention! I’ve revised each question/explanation accordingly.

Question 41, wouldn’t the firm pay $500,000 total? Reasoning: $1,500,000 million – $10,000 deductible = $1,490,000 remain. 1,490,000 – 1,000,000 million policy limit = $490,000 remaining to be paid by firm. $10,000 deductible + $490,000 after policy limit = $500,000 total paid by firm.

Thanks for your question @vmancera! I get where you are coming from, as I was scratching my head on this one too. I got some clarification from one of our subject matter experts, so here is the justification:

The deductible is the first $10,000 that gets paid prior to insurance kicking in. Then, insurance will cover up to $1 million (including the deductible, so insurance ultimately pays $990,000), then the firm pays the remaining $500,000. Therefore, the firm pays $510,000 total.

Hope this helps!

Kiara Galicinao, AIA, NCARB
Black Spectacles

For Question 28: if I put all the AIA documents mentioned in order, would they go in the following order?

  1. B101
  2. C401
  3. A701
  4. A101
  5. A201
  6. G701
  7. G703
  8. G704

Hi @auhe,

Welcome to the ARE Community and thank you for your questions! Yes, generally this is the correct sequence of those mentioned AIA contract documents following the traditional design-bid-build project delivery method.

Note that G701 Change Order would be used only as needed for an agreed-upon change to the contract scope, so it could be used at any point after the construction contract is in place (i.e. either as Step 6 or 7 in your list).

G703 Continuation Sheet is used as part of the G702 Application and Certificate for Payment process.

Hope this helps!