In the A201 General Conditions, it states the contractor is responsible for paying for permits and special inspections. But the IBC Section 1704.1 states owners or their agents shall employ an approved agency to perform special inspections, removing any appearance of a conflict of interest with the general contractor paying for inspections of their wor