In the A201 General Conditions, it states the contractor is responsible for paying for permits and special inspections. But the IBC Section 1704.1 states owners or their agents shall employ an approved agency to perform special inspections, removing any appearance of a conflict of interest with the general contractor paying for inspections of their wor
Related topics
Topic | Replies | Views | Activity | |
---|---|---|---|---|
Exam 3 Question About who secures permit | 2 | 520 | July 10, 2021 | |
Who pays for tests/inspections rule of thumb? | 2 | 1076 | November 30, 2021 | |
AIA A201 - General Conditions - Owner, Architect & Contractor? | 1 | 1027 | May 24, 2021 | |
Practice exam 4 question 59 | 2 | 620 | June 18, 2021 | |
C&E Practice quiz | 7 | 10500 | May 17, 2023 |