ARE PjM Practice Exam

Can someone help explain to me how this is the answer?

The question is asking about the " Record Document " that will be submitted to Arch and related to the modifications. Addenda is a modification prior to contract execution, punch list and contractor’s payment application are general and not specific to the changes. BCD will document the changes.

Ah. I see. Key word here is record documents.