CE PRACTICE EXAM 1 Case Study 2: Question 8 of 8

The question is The town intends to obtain LEED certification for the transportation hub as a LEED transit project.

Which of the following items must the contractor provide in order for the project to be considered for certification?

and the answer is : Excavation management plan

Generally I had a hard time understanding this case study- but this last question- I did not understand at all. Can you explain?

Thank you

@sevanb As the answer explanation states, the transit scorecard indicates a demolition waste and excavation management plan is required. Refer to the LEED Transit reference in the case study and navigate to the section titled Materials and Resources.

In addition to reviewing the correct answer explanations, it is also very helpful to review the incorrect answer explanations. This gives you a better understanding of the context and why one answer may be a better choice than another.

Hope this helps!

Kiara Galicinao, AIA, NCARB
Product Coordinator
Black Spectacles

1 Like