What is included in the total cost of work?
Property cost?
All site work?
Contingencies?
Removal of hazardous waste?
Contractor’s fees?
Contractors overhead?
What is included in the total cost of work?
Property cost?
All site work?
Contingencies?
Removal of hazardous waste?
Contractor’s fees?
Contractors overhead?
Hi @ssimenhoff02 ,
Check out B101. The cost of work is defined in article 6.
We did a webinar on this topic a few weeks ago that might be helpful to you. Check it out at the link below.
Hope this helps!
-Darion
Thanks Darion this is super helpful. Just to follow up, can you clarify on the section for “rights-of-way”. Does this mean that any site work having to do with utilities for example, or something located in an easement, will not be included in the cost of the work?
Hi @ssimenhoff02 ,
Right-of-way in this section refers to the cost to secure any right-of-ways or easements. The cost of any work occurring within the right-of-way will be included in the cost of the work.