Practice exam question- day 23 - see question below

@kiaragalicinao In the practice exam day A project is being executed under AIA A201. The architect’s team must have a clear understanding of what is included in the contract documents as part of the contract between the owner and contractor.

Which of the following are included in the contract documents? Check the four that apply.

This one was tricky because in the video i found with contract documents, construction docs and project manual from the videos in PjM- they show ALL contracts in the video(A-101 201 B-101) all as part of the Contract documents. The addenda is also included. Specs and supplementary conditions. SO there are 5 CORRECT here and not 4!

Why would I have not chosen the B-101? ( is it because we are asking specifically with the CONTRACTOR and the owner? why would the video have the B-101- as contract documents are mostly for the contractor.